Region of Queens — Liverpool, Caledonia, & Greenfield

Cycling Nova Scotia is partnering with the Region of Queens to improve walking, rolling, and cycling connections!

About the Project

Cycling Nova Scotia works alongside communities to develop grassroots Active Transportation (AT) plans that reflect local needs, priorities, and visions for the future. Our approach is rooted in collaboration, ensuring that residents, stakeholders, and municipal leaders are active participants in shaping a more connected, accessible, and sustainable community. Through meaningful engagement, we help communities identify opportunities to enhance their walking and cycling networks, improve safety, and create vibrant public spaces that encourage active travel for people of all ages and abilities. The result is a locally informed strategy that not only strengthens transportation options but also deepens community ties—making active mobility a natural, enjoyable, and essential part of everyday life.

What’s coming up? Share your communities vision!

Phase 1 – Spring Engagement

Survey Opens June 24, 2025! Stay tuned for the link [here].
Network Design! Stay tuned for the link [here].

June 19, 2025Focus Group Session
Location and time: TBD
June 24, 2025 – Online Survey Open
Location and time: TBD
July 4, 2025 – Engagement Session
Location and time: TBD
July 5, 2025 – Pop-up Engagement
Location and time: TBD

July 6, 2025 – Pop-up Engagement
Location and time: TBD

Phase 2 – Summer Engagement

Survey Opens June! Stay tuned for the link [here].
Concept Designs! Stay tuned for the link [here].

July 16, 2025 – Focus Group Session (Online)
Location and time: TBD

Project Timeline

Phase 1: Visioning and Network Planning
(June – August 2025)

  • Community Engagement 
  • Stakeholder Workshops
  • Network/Route Engagement
  • Deliverable: “What We Heard” Report & Draft Network Plan.

Phase 2: Conceptual Design
(September – November 2025)

  • Developing Class D (Concept) Designs
  • Stakeholder Engagement
  • Concept Design Public Engagement
  • Deliverable: What We Heard” Report and Design Drawings.

Phase 3: Advanced Design & Costing
(December 2025 – June 2026)

  • Refinement to Concept Designs
  • Consultant Engineering & Traffic Studies
  • Finalization of Cost Estimates
  • Deliverable: Final Design & Costing 

Phase 4: Implementation Community led
(October 2026 – Ongoing)

  • Grant Applications & Funding Strategy 
  • Municipal & Provincial Approvals 
  • Construction
  • Monitoring & Oversight